Week 42 · 11–15 Oct 2026 · Optimized for 06:00–11:00 low-ambient windows
Maintenance Planner
Work orders
18
Crew hours
54
Planned spend
QAR 1.80M
Risk avoided
QAR 6.78M
Crew schedule
Sun 11
Mon 12
Tue 13
Wed 14
Thu 15
Mechanical A
Mechanical B
Electrical
HVAC
Instrumentation
Work order queue
| WO | Asset | Task | Crew | Slot | Priority | Cost |
|---|---|---|---|---|---|---|
| WO-77120 | CT-106 | Conduct thermographic survey of connections | Mechanical A | Sun 11 6:00 | P1 | QAR 83.6K |
| WO-77121 | CH-128 | Run oil change and particle analysis | HVAC | Mon 12 9:00 | P1 | QAR 172.7K |
| WO-77122 | P-126 | Inspect and replace mechanical seals | Mechanical A | Tue 13 12:00 | P1 | QAR 35.3K |
| WO-77123 | M-151 | Replace intake pre-filters and upgrade to F9 media | Electrical | Wed 14 6:00 | P1 | QAR 5.9K |
| WO-77124 | C-104 | Replace drive-end bearing set within 5 days | Mechanical A | Thu 15 9:00 | P1 | QAR 79.8K |
| WO-77125 | C-136 | Reduce load during 12:00–16:00 peak ambient window | Mechanical B | Sun 11 12:00 | P1 | QAR 121.3K |
| WO-77126 | M-130 | Inspect and replace mechanical seals | Electrical | Mon 12 6:00 | P1 | QAR 12.8K |
| WO-77127 | CH-119 | Inspect and replace mechanical seals | HVAC | Tue 13 9:00 | P1 | QAR 213.9K |
| WO-77128 | P-108 | Inspect and replace mechanical seals | Mechanical A | Wed 14 12:00 | P1 | QAR 15.6K |
| WO-77129 | TX-116 | Inspect and replace mechanical seals | Electrical | Thu 15 6:00 | P1 | QAR 203.1K |
| WO-77130 | AHU-116 | Replace intake pre-filters and upgrade to F9 media | HVAC | Sun 11 9:00 | P1 | QAR 37.3K |
| WO-77131 | CT-116 | Recalibrate pressure transducers | Mechanical B | Mon 12 12:00 | P1 | QAR 30.1K |
| WO-77132 | TX-119 | Inspect and replace mechanical seals | Electrical | Tue 13 6:00 | P1 | QAR 231.7K |
| WO-77133 | P-121 | Conduct thermographic survey of connections | Mechanical B | Wed 14 9:00 | P1 | QAR 11.1K |
| WO-77134 | TX-108 | Recalibrate pressure transducers | Electrical | Thu 15 12:00 | P1 | QAR 238.7K |
| WO-77135 | CH-103 | Recalibrate pressure transducers | HVAC | Sun 11 6:00 | P1 | QAR 43.1K |
| WO-77136 | CT-103 | Perform coil cleaning and anti-corrosion coating | Mechanical A | Mon 12 9:00 | P1 | QAR 77.6K |
| WO-77137 | TX-117 | Rebalance motor phases and inspect terminations | Electrical | Tue 13 12:00 | P1 | QAR 187.3K |